October 2021
The Hills Apartments are well underway!
Windows have been installed on the ground floor, level one and level two. We are expecting the final set of windows and sliding doors to be installed in November.
Air-conditioning, plumbing, sprinklers and electrical installations have commenced. We are now preparing to start lining the walls and ceilings.
Scaffold is now installed around the building. We are expecting the installation of bricks to begin in November.
Concrete balconies are nearing completion and final roofs are being framed up in the coming days.
We are expecting the construction for the entrance foyer to begin in November.
Car park
COVID has posed some challenges with materials and labour stuck in Auckland. In saying this, the structural steel is complete and the final section of the roof structure has been installed.
Construction of the store rooms have commenced and services to underside of the slab is nearing completion, this includes, plumbing, power and sprinklers. The carpark is scheduled to be completed prior to the end of the year.
Hills Office Building
The foundations of this building are about to commence, including structural steel frame installation likely to begin in the new year.